top of page
Dec 27, 20221 min read
Big Horn - House Stakeouts
We're getting closer each week! The Surveyor stakeout the property based on engineer drawings and foundation package is out for bid.
10 views
Dec 9, 20221 min read
Lakeway Lease House - Framing Update 3
Continuation of framing on the Lakeway Lease house project!
11 views
Dec 2, 20221 min read
Lakeway Lease House - Framing Update 2
Continuation of framing on the Lakeway Lease house project! The overall framing is completed along with progress of wood sheathing and...
8 views
Nov 29, 20221 min read
Big Horn - Site Prep Continued
Continuation of site prep and stabilization. Today we observed additional erosion control along with the rock entrance and site excavation.
11 views
Nov 29, 20221 min read
Motif - Vinyl Plotting
To expand our in-house capabilities, we decided to place a small investment into a vinyl plotter.
3 views
Nov 18, 20221 min read
Lakeway Lease House - Framing Update 1
Continuation of the first week of framing on the Lakeway Lease house project! We're always amazed on the speed of framing. Did you know?...
3 views
Nov 16, 20221 min read
Lakeway Lease House - Framing Begins
First week of framing on the Lakeway Lease house project!
1 view
Nov 9, 20221 min read
Lakeway Lease House - Framing Supplies
As the foundation cures, the project took delivery of various building material, including decking, treated lumber and LVL beams. Framing w
2 views
Nov 2, 20221 min read
Dripping Springs Refresh - Interior Renovation Progress
Today we observed additional progress on the new shower and window placement. A majority of the gypsum work was completed, including the...
2 views
Oct 26, 20221 min read
Lakeway Lease House - Foundation (Garage) Update
Today we observed the completed foundation for the detached workshop garage (about a week after the house foundation was completed).
5 views
Oct 19, 20221 min read
Lakeway Lease House - Foundation (House) Update
Today we observed the finished slab, including anchor bolt locations and the areas with a broom finished.
15 views
Oct 18, 20221 min read
Lakeway Lease Home - Slab Update
Exciting progress to share! Today we observed the concrete foundation being set in place.
1 view
Oct 17, 20221 min read
Big Horn - Site Prep
On this beautiful day, we observed the placement of silt fences and erosion control on the Big Horn site.
10 views
Oct 13, 20221 min read
Lakeway Lease House - Rebar and Foundation Update
Today, we observed some of the rebar progress on both the house and garage. This included rebar ties, stirrups, chairs and waterproofing.
6 views
Sep 9, 20221 min read
Lakeway Lease House - Underground Plumbing and Electrical
Underground construction involves more than just buried conduit and plumbing lines. It requires coordination between several trades.
4 views
Sep 4, 20221 min read
Lakeway Lease House - Foundation Updates
Today we photographed the foundation progress, including the formation of interior grade beams and waterproffing.
8 views
Aug 22, 20221 min read
Lakeway Lease House - Foundation Start
Rough grading started this week along with temporary formwork for the concrete foundation.
6 views
Aug 19, 20227 min read
Motif Articles: Residential Fire Suppression - NFPA 13D Systems
NFPA 13D is a residential sprinkler design standard focused on one- and two- family dwellings and manufactured homes.
7 views
Aug 18, 20221 min read
Lakeway Lease House - Mobilization and Site Update
Site mobilization, foundation stake out and temporary power on site.
8 views
Aug 15, 20224 min read
Motif Articles: Austin McMansion Requirements
The "McMansion" regulations, were designed to minimize the impact on surrounding properties in residential neighborhoods.
14 views
bottom of page