top of page

Big Horn - House Stakeouts

Updated: Apr 25, 2023

Small... but a critical step completed! Today we observed the placement of survey markers, often referred to ask "stakeouts". This process will be repeated several times through the projects as this property has many challenges based on the current topography contours.


The surveyor referred to the construction documents to map certain areas for reference. This will allow the foundation crew to pinpoint exactly where the formwork will be placed.


Because the site requires a significant amount of "cut and fill", the surveyor will need to return several times to ensure the structure is placed as shown in the drawings.


Stakeout provided by the Surveyor
Stakeout provided by the Surveyor


Aerial of construction progress and Lake Austin
Aerial of construction progress and Lake Austin
Construction progress on Lake Austin
Construction progress on Lake Austin

Annual (temporary) rye grass helps retain the sandy loam from run-off. We also find its a somewhat of a courtesy to the neighbors too.


Example of a marker
Example of a marker

 

To learn more about this exciting project, please check out our project page.




9 views0 comments

Recent Posts

See All

Comments


Commenting has been turned off.
AdobeStock_491473646.jpg
Thanks for subscribing!
bottom of page